Tuesday 12 June 2012

Lock Up

I've been away for work for a few weeks and the house has progressed well. Cladding, rendering, electrical and plumbing rough in was completed. Here are the progress shots.

The nomenclature for the lock up stage is somewhat misleading, so for those interested;

Lock up Stage – means when the home’s external wall cladding and roof covering is fixed, the flooring is laid and external doors and external windows are fixed (even if those doors or windows are only temporary).



Front facade - Daniel Robertson London 50mm & Dulux Stepney render
Bristile Classic Charcoal Tiles, Rylock Charcoal Windows, Dulux Monument Fascia & Gutters
Render basecoat. Who chose the meter box colour?  Hmm, guess we'll have to re-spray this after hand-over.




2 comments:

  1. Hi there, Don't worry about the meter box, I thought the same thing, but the painter will paint it for you. Cheers xx

    ReplyDelete
    Replies
    1. Thanks for the heads up. Is that all builders? I guess we'll find out soon enough.

      Delete