The timing largely depends on the time taken to build, but
with the average build (for our builder) taking between 9 - 12 months, it makes
sense to do site preparation and footings late spring Oct/Nov. The ground is
dry enough to dig footings/pour concrete, but not so dry it's impossible to
dig. Assuming everything else goes to plan you should be at lock-up with the
roof on late April, before any substantial rain in May/June.
In our case we got a lot of rain in May before the lower
roof tiles were laid and we had a lot of water in the house. The water isn't
that much of a problem, as I'd read somewhere that the yellow tongue can be
submerged for 3 months, but you need it to be thoroughly dry before plastering
starts so this did delay our plastering by a few weeks.
No comments:
Post a Comment